3.2 Construction (Design Management) regulations path safety systems

Illustration

Why do I need a safety system?

By taking on the task of managing paths in the Scottish mountains you are also taking on the responsibility to minimise the risk posed by natural hazards, work activity and path design. This legal duty of care applies equally to all building work, including pathwork, and is set out in the Construction (Design and Management) (CDM) Regulations 1994. To work safely, and comply with CDM regulations, a path safety system must be applied to every site and every path management project.

Safe sites do not happen by accident, but accidents do happen on unsafe sites.

CDM regulations do apply to path construction activity. CDM applies to any commercial or public construction work that takes more than 30 days to complete or involves more than five workers on site. In practice, all access projects require risk assessment, careful design, well-supervised site work and some form of reporting back; therefore, a common path safety system is applied to all sites and projects. This system also meets the needs of CDM.

The effort and time spent on safety planning and preparation will obviously be less for regular tasks on a well-known site – such as a quarterly maintenance visit – and much more extensive and complex on the rebuilding of a new site – usually involving formal design work, competitive tendering and specialist path contractors. Whatever the project, a safe site requires thorough and constant application of a path safety system.

What are my safety objectives?

Having a safe access site involves many factors: a good design, the right materials, well-trained workers, the right tools for the job, a first-aider, the weather, not having visitors wandering about. The objective for the path manager is to bring all these things together by planning ahead, minimising risk, communicating, coordinating and reviewing:

It is neither possible nor desirable to render a mountain path totally safe. Rather, the aim is to understand and predict the hazards inherent in working on a steep, remote and exposed hillside, and to fit into this testing environment by working at the right time, with good techniques and well-trained staff. Often, this involves working with the environment by using on-site materials, working only in the summer and not working in wet conditions. Safe working must largely respond to and work around natural hazards, and not try to eliminate them through overconstruction or heavily mechanised working.

Path management has generally a good safety record both for work teams building the paths and for the public using paths after they have been repaired. Most workers are motivated, considerate and attentive to safety.

Working on path repair is very different from going for a walk in leisure time. Whatever the terrain, when at work HSAW 1974 always applies. The employer is responsible for ensuring all work is carried out as safely as is reasonably possible; the employee is responsible for working safely and not putting others in danger. Under CDM Regulations, construction work carried out on a mountain requires a safety plan to be prepared and operated and overseen by a Planning Supervisor. There is no exception to this rule.

Compared with building work on a flat lowland site, mountain pathwork is a relatively simple type of construction, but takes place in a remote and uncontrolled environment. Pathwork tends to use few chemicals or power tools and has little subcontracting, but work takes place on steep slopes, in poor weather, in the middle of nowhere. Conventional safety planning often focuses on building materials and handling, whereas for mountains the focus is weather, fitness, remote communication and even navigation! Select the key hazards for your sites and concentrate most effort on understanding and minimising exposure to them.

The safety plan should focus on avoidance of risk. Once key hazards are identified and understood, think about the factors which increase or decrease risk. The weather is seasonally affected and changes daily, therefore it may be best for work to take place between May and September. The weather forecast can be faxed to the teams every morning and the tasks that are safe for that day can be decided. On wet days, borrow pits and surfacing will be safer than boulder moving on a steep slope.

Safety takes precedence

For work to start in May, tenders will have to go out in January, which may not fit well with the financial year starting in April. Such administrative arrangements will have to fit around safety considerations for both the organisation and the timing of work. This also extends to external organisations such a grant-awarding bodies, which will have to take decisions in time for safe working to commence. If decisions are delayed, the only additional considerations should be financial; there should be no attempt to complete work that season, and the risk should not be increased on site by work extending into winter.

Who does what

Working safely requires a team effort. CDM is targeted at improving communication among all those involved, and the regulations set out clearly defined roles, each with specific responsibilities. In pathwork, the key role of planning supervisor is usually taken on by the project manager – this is the most complex role and usually requires both training and supervision for it to be performed effectively and to prove ‘competence’ as required by the act. It is the norm in access project management for more than one role to be taken on.

Title in CDM regulationsKey responsibilitiesWho performs it in pathwork?
The clientAppoints competent designer/planning supervisor, maintains final buildSite owner or factor; Public body or charity
The designerAssess and design a structure that is safe to use and safe to constructPath surveyor; Path manager
The planning supervisorSupervises project, prepares safety plans, communicates, notifies HSEPath manager or in-house/consultant specialist.
The principal contractor safe working on site.Prepares risk assessments and manages company leaderTeam leader or contract
Health and Safety ExecutiveReceive Safety plans, ensure compliance, provide adviceLocal HSE field office

Devising your own safety system

There are many systems for managing safety, each adapted to the needs of particular industries, types of construction and administrative arrangements. In access and outdoor construction work there are three main approaches:

What to include

Safety planning does not have to be a complex or onerous task. The essential/minimum stages required in the process are:

Several simple and very useful steps can be added, particularly if the main contract is let to a team that is separate from the managing organisation:

Some things are unnecessary and overly complex in a safety procedure, for example:

Pointers

Whatever safety system you decide to develop and use, there are some pointers on good and useful practice which may help:

Training and support

Whoever takes on the duties of planning supervisor must be able to demonstrate their competence for the job. Competence includes factors such as experience, training and demonstrated ability. There are several ways to gain the knowledge needed and to keep it current and up to date:

Example project timetable: Annat to Coulags

ANNAT to COULAGS: the safety process from first survey to long term maintenance….
DateDocumentsWho was involvedSee sub-section…
Photo
Survey2.5 Red surveys
First site visit4.2 Preparing a competetive tender
Design and spec4.2 Preparing a competetive tender
Pre-tender plan3.3 Safety assessment
Tender site visit3.4 Risk, hazard and control
Method statement and risk assessment3.4 Risk, hazard and control
Contract selection3.6 Safety performance
Safety Plan3.6 Safety performance
Work start meeting3.7 Maintaining site safety
During the contract…site visits3.7 Maintaining site safety
Close contract3.7 Maintaining site safety
Safety file3.7 Maintaining site safety
Maintenance and safety audit3.7 Maintaining site safety