1.2. Environmental Impact

Introduction

Most upland paths will have a visual impact on the landscape, whether there for traditional access for stalking, or for the simple pleasure of walking in an appealing mountain environment. The paths that exist today are predominantly there for outdoor recreation, through the rise in popularity of hill walking, concentrated on particular mountains. Increasing and excessive use has resulted in wear and serious erosion, with some very large and obtrusive scars causing unacceptable visual impact.

This has lead to the need to build or repair paths in a way that minimises the impact of use and erosion, and restores sites to an acceptable and durable state. Only when this is done can access be sustained and environmental benefits seen.

Approach to Pathwork

The best way of reducing the environmental impact of pathwork is to make sure that quality work is carried through - from initial design to finished pathwork. This will be achieved through effective planning, taking into account path use and site characteristics. To ensure that best solution is found and environmental requirements met, it is essential that a path assessment is carried out prior to any work on the ground.

A minimalist approach of regular maintenance and minor pre-emptive work, incorporating durability, is generally accepted as being preferable and most appropriate. However, in many cases, often due to a lack of maintenance, the impact of erosion has already exceeded what is acceptable and urgent major repair is necessary. This will still require maintenance and monitoring to ensure that no major problems re-occur.

Repaired section of damaged stalkers path

Repaired section of damaged stalkers path. On-site boulders, turf and aggregate used to mimic the original 19th century design. Coire Dubh, Glen Torridon. See path assessment for the path pre-repair work.

Design

To avoid failure, and subsequent increased environmental impact, pathwork must be designed to cope with the pressures exerted on it, by climate and users. The design should ensure that the quality of finished work is of the highest standard with techniques selected to blend in with the surrounding landscape.

Materials

Materials should be natural and selected to blend with the landscape.

Where local material cannot be used or is not available, stone or revegetation material may have to be imported to the site.

Timing

Pathwork should be carefully planned to avoid further damage to the site. Programme work to take place at times of the year when the ground conditions are dry and stable-working on water-logged, soft soil and fragile vegetation can result in rapid damage.

Access

Routes to the site for daily access should be carefully chosen, normally using the existing path line. Where this is not practical the route selected should be varied to avoid establishment of alternative path lines.

Remote Working

Where on site accommodation is required for remote working carefully consider the positioning and potential visual impact. Ensure there is adequate provision and resources, for minimising visual intrusion, waste management, and re- instatement and tidying of the site on completion of the pathwork.

Construction

The impact of undertaking pathwork should be carefully controlled to avoid further damage to the site.

Liaison and Permissions

It is essential to have the appropriate permission and approval for works, especially on environmentally sensitive sites - if in any doubt ask. Lack of communication between the appropriate interests can give rise to misunderstandings and inadvertent environmental damage. Those who should be approached include: