4.2 Preparing a competitive tender

Illustration

What is a competitive tender?

When a path needs to be built, or some other access project undertaken, the organisation commissioning the work (the ‘Client’) will ask several suitable teams (the ‘Contractors’) to assess the project, discuss it if necessary and provide a proposal and price for carrying out the work. The documents that each contractor submits (usually a letter, some notes, a safety plan and a project plan) is called the ‘tender’, and ‘competitive tendering’ is the process of communication between the client and the contractors that leads to one team being chosen for the job.

All the common types of contract used in pathwork can be suitable for competitive tender – all that differs is what is actually being priced and competed over.

Type of contract

In summary, it is possible to select the most suitable type of contract for any particular job while still adhering to competitive procurement policies.

Good competitive tendering depends on having a ‘level playing field’ for all contractors. All contractors have the opportunity to prove their competence and join the pool of selected contractors, and all chosen contractors receive the same information and have the same opportunity to bid. A good specification should mean that the needs of the client will be met whichever team is chosen. Good competitive tendering is about ensuring that the best bid is selected and that this is done through a fair and consistent process.

What does a successful tender contain?

Path contracting companies win work by submitting successful tenders. They are assessed primarily on the information they submit for each new job, backed up by other information and their track record. Well-thought-out tenders often do best: four to eight pages containing all the information requested plus some original thoughts on how best to perform the key tasks is sufficient. Teams that are very able on site often do not show their abilities and expertise at the tender stage. Only by demonstrating the necessary knowledge at the planning stage will contract teams get the opportunity to prove it on site.

From the point of view of the client, the offer to carry out work (a ‘tender’) is most likely to produce a successfully delivered project if it can demonstrate:

Successful tender preparation requires good communication between the parties involved: this includes an easily read and succinct tender submission.

Preparing a tender: a six-step process

Preparing a good tender involves information-gathering and decision-making. It is better to prepare the tender systematically. A good tender for a medium-sized contract worth £20,000 will take 2 or 3 days’ work to prepare, spread over a period of 2 or 3 weeks.

Information needed
Decisions
Source of advice
1
Work plans; information on other jobs coming up; diary; advance warning of tender; brief description of the job.
Do you want to bid for the job?
Team leaders
Other potential clients
Project client
2
Site plans; bill of quantities; on-site information on materials, design, use and conditions.
Is it feasible, having seen the site?
Project client
Site owner
Local contractors
3
Detailed design for each element; good idea of team skills and productivity; plant, materials and other costs.
How much will it cost you to deliver?
Project client
Supplier companies
Specialist advice
4
Contract details; your own project plan; site information; team certificates; path ‘portfolio’.
Can you meet all the conditions?
Safety consultant
Training provider
Statutory agencies
5
Cashflow forecast; weather trends; feasibility analysis.
Is it a risky job?
Accountant
Local site knowledge
6
Client decision and feedback.
Is your bid the best?
Project client
Training ‘mentor’

At each stage of the process decide whether you wish to proceed – only continue if you still want the job, believe that you can win the tender and think that you can make a profit. You can drop out of the tender process at any stage, and usually up to 30% of bidders do, but you must let the client know immediately: failure to respond by the closing date will not create a good impression for the next job.

Step 1: Do you want to bid for the job?

When you are asked to bid for a pathwork contract, make a brief assessment of the contract and specification and then decide whether to prepare a bid. There are usually between three and six companies competing. Making a bid is a time-consuming process. A tender for a medium-sized path contract will take 2 or 3 days to prepare: 1 day for a site visit and at least 1 day for making calculations, taking advice from the team and subcontractors and preparing the bid paperwork. So ask yourself the following questions: Are you available when work is required? Is your team good at this type of work? Do you really want the job? Preparing a few thorough tenders for the jobs you want is more likely to win work than submitting rushed bids for every job possible.

It is good practice to evaluate invitations against predetermined criteria, although there will obviously need to be some flexibility. Some factors to consider include:

Appraise the tender as early as possible after receiving the invitation as you will need plenty of time for the subsequent stages. Do not spend any further time on a job you do not wish to bid for. Keep the client informed of progress and seek extra information on any points that are unclear. Explain to the client your team’s abilities and areas of special interest, as this will be useful in planning future work and helps build up a good working relationship.

Step 2: Is it feasible having seen the site?

A detailed site visit is required to assess properly almost any path job. It is good practice to attend a pre-tender site meeting for the potential contractors and the client, and many clients will only accept bids as ‘competent’ if you have attended. It is preferable that all contractors visit the site on the same occasion. This allows the client to explain to everyone exactly what is required and answer questions raised. It is also a good opportunity to demonstrate your knowledge and put forward ideas.

Normally the specification will be reviewed by several experts, often resulting in minor amendments being made. It is essential that any amendments to the design or bill of quantity are confirmed in writing to all those invited to tender as soon as practical after the meeting, so that everyone is bidding for the same revised job.

Step 3: How much will it cost to deliver?

Price is a key part of any tender; being able to estimate costs accurately is key to setting the price and deciding whether there is a margin for leeway and some profit. With the advent of ‘Best Value’ contract selection, price is a significant factor in choosing who gets the job, but it is not the sole factor. For many pathwork jobs a good team at a reasonable price is a better option than an inexperienced team at cut price.

Cost estimation has several elements:

Estimating the cost of works is a complicated task, and different contractors may adopt different approaches. Consider the options of using different types of plant or other working methods, such as airlifting materials. This may have an impact on your costs and the price for providing the optimum quality–price ratio. Air-lifting materials may be more expensive, but it will create less disturbance to the site, and this may be of prime concern to the client. Talk to the client and consider offering two options and prices.

Step 4: Can you meet all the conditions?

Contracts contain detailed conditions on how work will be carried out. Some, such as safety and insurance, are fixed for all jobs. Some, such as work within designated conservation sites or access arrangements, vary from site to site. Others, such as working hours and completion dates, may be flexible and can be set by the contractor. The client will often provide a checklist of information to include or a tender questionnaire to complete. If you are uncertain, be sure to cover the following basics: dates, team personnel, track record, plant and materials, price, project plan or method statement.

Give the planned start and completion dates for the job and your usual working days and hours. The contract usually gives a ‘window’ within which work must be completed, often constrained by weather or land use, such a stag stalking seasons.

Make sure that you provide all this information and any additional requested – it is surprising how many bids are incomplete, and these are the first to be rejected. If you are unable to meet any of the conditions contained in the contract, or are uncertain about how they apply, then bring this to the attention of the client and include this in your covering letter. However, do not make your bid a ‘conditional offer’ by saying that it only applies if certain conditions are met – clients do not like this approach.

Be positive and concentrate on preparing a good method statement: this is a great opportunity to show the client that you have thought through the contract. Having a plan that is prepared and ready to deliver could put your bid ahead of a lower cost but less well-planned competitor. Many successful contractors submit a detailed method statement for every major contract, whether the client requests it or not.

Step 5: Is it a risky job?

All projects contain some level of risk. The price you bid depends on assessing the risks and opportunities the job represents to your business. Contractors can make a profit or loss depending on how accurately the risks have been assessed. Before submitting a tender, the risks and opportunities involved must be identified and assessed.

Risks include: financial, adverse conditions, poor weather, reputation, suppliers.

On the other hand, the tender may offer opportunities, including:

The price you bid will depend on many things: if you think there is a high chance of weather lay-offs, increase the price by 10–15% and seek reassurances on being given extra time to complete the job. If you need work urgently and want to impress a new client cut the price by 5–10%. Always set your bid price at a level that more than covers all costs, and never go below this. Add a margin to your total expected costs that gives you room to manage the variables and make a profit if you are successfully able to do this.

Look around at the other teams bidding and particularly the availability of skills at the time the client needs the work done – many larger client organisations prefer higher prices to delayed work. Your price should cover all work anticipated, including site restoration and return visits for any remedial work (usually 3–4% of the construction cost). Do not bid a low ‘core price’ with the expectation of adding plenty of extras when on site – clients will be looking for a realistic, single price that reflects all that the job demands.

Step 6: Is your bid the best?

Submit your bid in the manner requested – often in two envelopes and with an electronic copy – and well before the closing date set. Ask the client how long a decision is likely to take: this can vary from 3 days to 6 weeks depending on the complexity and size of the organisation. There may be a long delay if the information is being relayed to grant aid partners for their approval, but the client should let you know if this is the case. You may be asked for additional information, and a prompt turnaround is essential.

The winning bidder will normally be contacted by telephone and given a brief period to confirm acceptance. Unsuccessful bidders will receive a letter a few days later. It is not standard practice for clients to disclose the winning bid price because of the relatively small number of teams bidding. Whether or not you are successful, contact the client for some feedback: you have spent several days preparing the bid, and feedback will aid your success next time.

Feedback from the client to contractors should include the following: price, quality of tender, future prospects.

Competitive tendering: some good practice pointers for contractors and clients

If you are in doubt about preparing a tender seek advice: talk to your local enterprise company; attend a short course; or approach an experienced firm and ask to shadow their work. Tenders for work are the most complex and important pieces of paper in pathwork: how you approach and prepare your bid not only tells others about how you do business, it is also a legally binding contract if you are successful and win the job.