2.7 STONE FORD

symbol - stone ford

Fords have been traditionally used on all access routes, from roads to hill tracks and stalkers paths, where wheeled vehicles or stalkers’ ponies require access. On upland paths this common feature has a stone pitched or cobbled surface, with variations in style from place to place.

Illustration

FUNCTION

The ford provides a solid, hard-wearing stone surface through rivers, large streams or burns, where bridges or stone culverts are not appropriate or feasible. It also serves to dissipate the waterflow by increasing the width of the watercourse, and possibly reducing the depth. A regular surface enables ponies and wheeled traffic to cross easily, and walkers to have a safer crossing, though probably a wet one. The whole structure should withstand fast flowing water, and also help prevent erosion of the river bank where it meets the path.

Bill of Quantities (example)

Using local weathered stone construct a stone ford, with a pitched surface lining the full length and width. Extend at least 300mm wider than the path on each edge, and to the top of each bank. Re-grade the path surface at least 2 metres either side of the ford.

POSITIONING OF THE FORD

Illustration

This will obviously be where the path crosses the watercourse, which may limit the option of choosing the best place. The ideal position for a ford is on a wide, level stretch of slower flowing water, where its force is reduced. This may mean re-aligning the path, or the burn. The ford should not be placed where walkers will by-pass it on dryer days.

CONSTRUCTION

Components

The pitched surface comprises the number of courses of stone required to run from the path on each bank down to the centre of the stream. The courses normally run parallel with the bank. These form the ford:

Dimension Guidelines

Dimensions of the ford vary according to the width of the watercourse and the width of the path.

Materials

Local block stone should be found within the area that the path passes through, and from the stream bed where this does not have an adverse impact on the flow of water.

The size and shape of all stone should be such that the depth can be pitched into the bed of the stream with a level tread surface on the top side. Other faces should be as even as possible, to form a tight match with adjacent stones.

The 'key' stones of the ford, edges and ends should have a minimum depth of 300mm, dug into the stream bed.

Method of Construction

Having assessed the dimensions required for the ford during high waterflow, the construction should preferably be undertaken during the period of lowest flow.

Step 1

Prepare the stream bed.

Step 2

Pitch the ford centre channel.

To provide a firm base, and achieve the required levels, start with the centre course of stones, at the lowest point of the stream bed. If the drop from each bank is minimal and the stream narrow, construction may start at the path edge.

Illustration

Step 3

Pitch the remaining courses.

Starting each adjoining course at the lower ford edge, pitch parallel courses, until the ford ends are reached, at the bank

Step 4

Re-grade and compact the path surface, over approximately 2m length, down to the level of the ford end stones on the stream bank, in order to achieve a draining fall towards the stream.

Step 5

Restore any damaged areas, particularly the path and stream bank edges above and below the ford, to ensure there is no risk of water flowing around the ford causing damage to the path.

TROUBLESHOOTING

Key points to watch out for:

VARIATIONS

Illustration

Where no wheeled traffic is expected the design can be varied by incorporating a defined step, at each end forming an edge to the path where it joins the ford. This would use large block stones butted tightly together. The ford becomes like a very large cross drain, with a wide stone liner - with large edge stones and water flowing below walking level.

This, or other designs, may also incorporate stepping stones to give walkers good footholds when the waterflow is particularly high. These may be the edge stones on a wide river, or a single large stone in the centre of a narrower stream.

If the ford is constructed where there is a steeper fall, such as where the path is traversing a steep cross-slope, it may be preferable to construct courses of stone running parallel to the path. The course on the down stream edge will require the largest stones, as the base of the structure.

MAINTENANCE TASKS

Fords should require minimal maintenance. They are self cleansing, and if constructed properly and soundly, should only require minor repairs. Maintenance should take place during dry weather.

ENVIRONMENTAL SENSITIVITIES

  • build a ford that will blend in with the surrounding landscape, using stone from the stream bed or surrounding ground
  • check that changes in waterflow will not affect the ecology down stream

HEALTH AND SAFETY HAZARDS

  • do not work on the ford when the waterflow is strong
  • be aware of slippery surfaces on boulders and stone underfoot

TAKE CARE

  • build a ford that is large and solid enough to prevent washout with the highest and fastest flows of water; in particular after sudden snow melt and long periods of rain.